Monitoring field performance of a tied-back secant pile wall

Tyler Morency
3 years ago

Monitoring field performance of a tied-back secant pile wall

The Peace River region in Northern Alberta is well-known for its complex geology which poses geohazardous risk to roadway and railway transportation infrastructure.

In this seminar video presentation, Leanne McLaren, a graduate student in the Master of Engineering program at the University of Alberta and geotechnical engineer at Thurber Engineering, details her research project. Her work is an analysis of geotechnical data collected before, during, and after a transportation infrastructure remediation project to stabilize a slope embankment along a stretch of Highway 2 in the Peace River region of Alberta.

In “Using Instrumentation Data to Assess the Performance of a Tied-Back Secant Pile Wall” we learn the goal of the project was to use instrumentation data to evaluate the effects of a secant pile wall on soil movement around the highway. This information is important because it directly addresses the causes of threats to the road’s structural integrity.

Slope movement on Highway 2

When Highway 2 was initially constructed in 1956, a section in the Peace River region passed over a particularly landslide-prone area. After it was built, slope movement quickly caused the road to drop several meters, leading to structural problems. As a result, the highway was realigned to avoid the terrain with the largest amount of expected movement.

Even after the realignment, slope movement continued to affect the highway. Since the 1990s, maximum yearly deflection in the ground around the site reached as much as 87 millimetres per year, demonstrating the major structural problems that still existed in the area. In 1998 a cantilever wall was constructed downslope of the highway in an effort to slow its descent. However, this wall was not able to sufficiently stabilize the terrain, and multiple cracks and dips formed in the highway due to a lack of support downslope.

In order to determine the scope of the danger posed by the continuing structural stresses placed on the road, multiple geotechnical investigations were carried out to evaluate soil conditions along the slope. These investigations revealed a slip surface located between a layer of medium-to-high-plastic lacustrine clay lying at a depth of between 6 and 17 metres below the surface and the stiff clay till underneath. Additionally, the water table was found to lie about 9 to 10 metres above the slip surface, which could accelerate weathering. This weathering would lead to the breakdown of cementation and a loss of cohesion.

Construction of the secant pile wall: Instrumentation monitoring

Because of the unstable ground conditions discovered by the geotechnical investigations, an additional wall was built to protect the highway from slope movement. A tied-back secant pile wall was built between 2015 and 2017 to resist the slip surface. It was created in six separate sections of varying depth with five rows of soil anchors to limit the degree of deflection as much as possible.

Example of the secant wall. Note the data acquisition system configured to automate data collection from the project’s instrumentation.

McLaren’s project used instrumentation data taken from the ground around the new wall to observe movement and verify design parameters. Instrumentation used before and during construction as part of the observational method included:

  • Inclinometer readings showed that maximum ground displacement increased steadily from 2015 to 2017. When the second wall was constructed in 2017, this movement stopped suddenly before picking up gradually, at a slower rate, until 2020.
  • ShapeArray readings showed similar trends. Deflections were reduced following the wall’s construction before accelerating again at a slower rate.
  • Pneumatic Piezometers to measure ground water levels.
  • Vibrating wire Strain gauges installed on the up and down slope of the cage showed multiple instances where microstrains on the concrete piles exceeded their hypothetical cracking moment. However, thanks to steel reinforcement in the concrete, the piles remained intact. Twenty-eight vibrating wire strain gauges were used during construction.
  • Vibrating wire load cells were used to measure loads on each anchor during and after construction.

Significance of the data

Data from these instruments show that the secant pile wall has provided the necessary added support against slope movement along Highway 2. After the wall’s completion, slope movement and deflections decreased. While the reinforcement is not perfect, current stresses are still significantly below the highway’s serviceability limit. 

What do the results mean for the future?

As slope movement beneath the highway continues to occur as expected, it is important to monitor the readings in case further intervention is needed to address the displacement. However, the data shows that the secant pile wall has been effective at keeping the highway serviceable. The instrumentation used in this project could be applied to similar situations throughout the highway system.

Leanne McLaren is a Geotechnical Engineer with Thurber Engineering in Edmonton, Alberta. Her technical interests include slope stability remediation, instrumentation, and foundation design. Outside of work, Leanne is passionate about promoting women and young professionals in engineering and has been an active participant with the Canadian Geotechnical Society as a member of the GeoVirtual and GeoCalgary conference organizing committees and the Southern Alberta Regional Director from September 2017 to December 2020. Leanne is also a singer and songwriter who enjoys horseback riding and ATVing around Alberta.

Have questions about secant pile wall monitoring with ShapeArray? Let’s talk.

  • 1993

    The Beginning

    Measurand is established in Fredericton, New Brunswick
  • 1994

    Bend sensor development

    Measurand develops and patents fiber optic bend and position sensors for the medical and automotive sectors

    U.S. Patent 5,321,257

  • 1995

    Canadian Space Agency

    Receives funding from the CSA to develop sensor technology that ultimately leads to invention of ShapeTape

    U.S. Patent 5,633,494

  • 1999

    Patent on fiber optic sensor

    Measurand receives patent for "Fiber Optic Bending and Positioning Sensor" issued June 29, 1999

    Canadian Patent 2,073,162

  • 2001

    ShapeTape & ShapeHand debut

    Measurand designs and develops innovative motion capture technology

    U.S. Patent 6,127,672, 6,563,107

  • 2002

    Measurand Attends the ICPMG

    First contact with the geotechnical sector at the International Conference on Physical Modelling in Geotechnics (ICPMG)
  • 2004

    ShapeArray

    Design patent application sent about a new product designed to meet the specific needs of the geotechnical industry

    U.S. Patent 6,127,672, 6,563,107

  • 2005-08

    ShapeWrap

    Measurand debuts ShapeWrap motion capture technology for the film and animation industry

    U.S. Patent 7,296,363

  • 2006

    Malibu installation

    ShapeAccelArray installed for ground monitoring for the first time​ in Malibu, CA

    Canadian Patent 2,472,421

  • 2007

    ShapeMRI

    Suite of instrumentation developed for motion capture within Magnetic Resonance Imaging (MRI) machines

    U.S. Patent 7,296,363

  • 2011

    SAAScan launched

    Built for rapid deployment and repeated use

    Canadian Patent 2,472,421

  • 2014

    SAAX launched

    Purpose-built for heavy-duty horizontal installation

    Canadian application 2,815,199 & 2,815,195

  • 2017

    SAAV launched

    The only geotechnical instrument with a patented cyclical installation method

    Cyclical Sensor Array, Canadian application 2,815,199 & 2,911,175